Despite state budget issues and shifting construction start and end dates a wide-range of transit projects are set to snarl commutes this summer. This includes ongoing mega-projects like the widening of the Jane Addams Memorial Tollway and the reconfiguring of the six-way intersection at Damen, Elston and Fullerton to numerous bridge replacements along Metra rail lines. Here is a survey of projects from the Illinois Department of Transportation, Illinois Tollway, Chicago Department of Transportation, Chicago Transit Agency, Metra and Pace.

Projects By Category

Bus

Rail

Highway

Road

Pedestrian

Currently in progress

Project Name Agency Description Areas Affected Cost Zip Codes Affected
CTA wireless access CTA CTA completed installing 4G wireless in its subway tunnels on its Red and Blue lines in 2015. The $32.5 million agreement was funded by four major wireless providers ¿ T-Mobile, AT&T, Verizon and Sprint. Loop, Streeterville, River North, Gold Coast, Old Town, Lincoln Park, Lakeview, Boystown, Wrigleyville, Uptown, Andersonville, Edgewater, Rogers Park, Bronzeville, West Town, Wicker Park, West Loop, Logan Square, Avondale, Irving Park, Jefferson Park $32.5 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616, 60611, 60654, 60610, 60614, 60657, 60613, 60640, 60660, 60645, 60626, 60653, 60612, 60622, 60642, 60647, 60608, 60618, 60630, 60641, 60646
Western Avenue bus CTA The return of express bus service to Western Avenue will come with a project that allows buses to communicate with traffic lights to hold green lights longer or to shorten red lights. The technology is called transit signal priority, and the cost is for the Western routes and an added route on Ashland Avenue. Auburn Gresham, South Side, Back Of The Yards, South Lawndale, Little Village, Lower West Side $27 million 60620, 60615, 60653, 60637, 60649, 60619, 60609, 60608, 60623, 60616
Ashland Avenue bus CTA The return of express bus service to Ashland Avenue will come with a project that allows buses to modify traffic signals when they are running behind. The technology is called transit signal priority and cost is for the Western routes and another added route on Ashland Avenue. Pilsen, University Village, West Town, Bucktown, Lake View, Wrigleyville, North Center $27 million 60612, 60622, 60642, 60647, 60608, 60607, 60657, 60613, 60618
Loop Link bus CTA, CDOT Work on the downtown bus rapid-transit system will continue, including protected bike lanes on Washington and Clinton streets. Loop $32 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
CTA rail fleet CTA The transit agency will continue to upgrade its rail fleet, a project that could add as many as 846 new rail cars. Chicago $2000 million
CTA bus fleet CTA CTA expects to begin receiving the first of the newest 125 buses as early as May 2016 in a project to overhauling or replacing nearly its entire fleet. The project will add 425 new buses total. Chicago $220 million
Lincoln Avenue test bus route CTA CTA will test service on the former Lincoln Avenue bus route. Details on location, service times and the length of the test haven't been determined. Lincoln Square, Ravenswood, West Edgewater, West Ridge, Lincolnwood Not available 60660, 60625, 60613, 60640, 60645, 60712
31st Street test bus route CTA CTA will test service on the former 31st Street bus route. Details on location, service times and the length of the test haven't been determined. Bridgeport, Armour Square Not available 60608, 60609, 60616
Red Line: 95th Street terminal CTA Work to rebuild the 95th Street terminal continues, including work on the 95th/Dan Ryan Station at the south end of the Red Line. Roseland, Chatham $280 million 60619, 60620, 60628
Red and Purple lines: Wilson Station CTA Rebuilding the Wilson Station on the Red and Purple Lines will continue. Uptown $203 million 60613, 60640
Washington-Wabash Station CTA, CDOT Work on the new Washington-Wabash Station will continue, combining the the stations at Randolph and Madison. Loop $75 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Quincy Station improvements CTA Two elevators will be added to the Quincy Station in the Loop, along with other accessibility improvements. Loop $15.7 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Ravenswood Connector improvements CTA Signals will be improved on the Brown and Purple line tracks between the Armitage and the Merchandise Mart stations. Ravenswood $32.6 million 60613, 60640
Green Line track work CTA Track work is scheduled between the Laramie and Harlem/Lake stations along the Green Line. Austin, South Austin, Forest Park, Oak Park $13 million 60644, 60651, 60301, 60302, 60303, 60304, 60130
Red/Purple Line modernization CTA In 2016, the CTA is moving forward with its massive Red and Purple line project, its largest capital project ever. The project would completely rebuild the Red Line from Belmont to Howard and the Purple Line from Belmont to Linden. Loop, Streeterville, River North, Gold Coast, Old Town, Lincoln Park, Lakeview, Boystown, Wrigleyville, Uptown, Andersonville, Edgewater, Rogers Park, Evanston Not available 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616, 60611, 60654, 60610, 60614, 60657, 60613, 60640, 60660, 60645, 60626, 60201, 60202, 60203, 60204, 60208, 60209
Red Line extension CTA Planning for the Red Line extension project from the 95th Street Terminal to 130th Street will continue this year. The proposed 5.3-mile extension would include four new stations near 103rd Street, 111th Street, Michigan Avenue, and 130th Street. Roseland, Fernwood, Pullman, West Pullman, Riverdale Not available 60619, 60620, 60628, 60643, 60627
Jane Addams Memorial Tollway widening Illinois Tollway The rebuilding and widening of the Jane Addams Memorial Tollway (I-90) between Rockford and the Tri-State Tollway (I-294) continues. The work this year focuses on the final 25 miles between Elgin and I-294. Elgin, Streamwood, Hoffman Estates, Schaumburg, Elk Grove Village, Rosemont, O'Hare $577 million 60666, 60107, 60169, 60179, 60192, 60193, 60194, 60195, 60196, 60159, 60168, 60173, 60007, 60009, 60018, 60120, 60121, 60123, 60124
Elgin-O'Hare western access Illinois Tollway Work this year on the Elgin O’Hare western access project will include improvements to the I-290 interchange at Illinois Route 390 and continuing construction of Illinois Route 390 between I-290 and Illinois Route 83. O'Hare, Rosemont, Wood Dale, Itasca, Bensenville, Medinah, Roselle, Hanover Park $384 million 60666, 60018, 60191, 60399, 60143, 60105, 60106, 60157, 60172, 60133
Reagan Memorial Tollway resurfacing Illinois Tollway A schedule to resurface I-88 from U.S. Route 52 to U.S. Route 30 hasn't yet been confirmed. Rochelle, Flagg, Ashton, Franklin Grove, Dixon $105 million 61068, 61006, 61031, 61021
Markham bus garage conversion Pace The Markham bus garage is converting to a compressed natural-gas fueling station. Markham, Harvey, Homewood $8.1 million 60426, 60428, 60430
Pace bus fleet Pace Pace's plans to purchase 91 compressed natural gas buses is stalled in the state budget standoff as the grant used to pay for the $466,000 vehicles is not funded. Markham, Harvey, Homewood $42.5 million 60426, 60428, 60430
I-90 express bus lane Pace When the work on the stretch of the Jane Addams between Elgin and Rosemont is complete, Pace will expand service along the corridor using a full-speed bus lane. In the meantime, work includes the construction of new park-n-ride lots and a pedestrian bridge and purchase of vehicles. Elgin, Hoffman Estates, Schaumburg, O'Hare, Rosemont $38 million 60666, 60169, 60179, 60192, 60193, 60194, 60195, 60159, 60168, 60173, 60018, 60120, 60121, 60123, 60124
Rosemont Transit Center Pace Work will expand the bus loading area at the Rosemont Transit Center. Rosemont $1 million 60018
Evanston bus garage Pace Work on the North Shore Division bus garage will allow buses to be moved to the Evanston garage from other garages in order to handle changes to Pace routes in coming years. Evanston $2.6 million 60201, 60202, 60203, 60204, 60208, 60209
Milwaukee Pulse line rapid transit Pace Final design and construction preparation is underway to provide bus rapid transit on Milwaukee Avenue in Niles and Chicago. Pace expects a construction contract to be approved in late 2016, with construction in 2017. Niles, Edison Park, Jefferson Park $15 million 60630, 60646, 60714, 60631
Elgin Transit Center Pace Renovation work on the Elgin Transit Center continues, including installation of real-time electronic bus arrival signs. Elgin $2.6 million 60120, 60121, 60123, 60124
Milwaukee Avenue improvements Pace Technology that can lengthen green lights and shorten reds to improve bus service is scheduled for Milwaukee Avenue corridor. Other areas are on tap for the years to come. Chicago $20 million
Bolingbrook park-n-ride lot Pace The park-n-ride lot in Bolingbrook is being expanded to accommodate bus-on-shoulder service on I-55. Bolingbrook $1.1 million 60440, 60490
Burr Ridge park-n-ride lots Pace The park-n-ride lot in Burr Ridge is being expanded to accommodate bus-on-shoulder service on I-55. Burr Ridge $1 million 60527
159th Street work IDOT Project includes resurfacing and redesign work, more lanes and intersection capacity, and bridge improvements along 159th Street in Homer Glen, Orland Park, Homer Township and Orland Township in Cook and Will counties. Homer Township, Orland Township, Homer Glen, Orland Park $105 million 60491, 60452, 60462, 60467, 60477
U.S. Highway 30 work IDOT One lane added in each direction of U.S. Highway 30 between I-55 and Illinois 59 in Plainfield, Plainfield Township and Jolliet. Plainfield, Plainfield Township, Joliet $21 million 60544, 60585, 60586, 60431, 60432, 60433, 60434, 60435, 60436
I-55 and Lake Shore Drive IDOT Six bridges are being rebuilt to add lanes and improve drainage, lighting and signage at the crowded interchange next to McCormick Place and Soldier Field. Near South Side, Lake Shore Drive $130 million 60616
I-90 and East River Road IDOT New bridge and road improvements at the I-90 exit onto East River Road. O'Hare, Norridge $10.1 million 60666, 60706
I-90 and Cumberland IDOT New bridge and road improvements at the I-90 exit onto Cumberland Avenue. O'Hare, Norridge $10.1 million 60666, 60706
Illnois Highway 171 bridge work IDOT The project includes fixing 20 bridges along Illinois Highway 171 in Lyons, McCook and Summit, including over Interstate 55. 2016 work focuses on northbound lanes. Lyons, McCook, Summit Not available 60534, 60525, 60501
Torrence Avenue bridge IDOT Replacing the Torrence Avenue bridge over Grand Calumet River, while adding bike lanes on the bridge and room for a bike path along the river. Burnham $11 million 60633
U.S. Highway 30 bridge IDOT The new U.S. Highway 30 overpass over EJ&E/CN railroad tracks in Lynwood is open, but roadwork on U.S. Highway 30 will continue this year. Lynwood $26.9 million 60411
Irving Park overpass IDOT Construction of a new rail overpass aimed at unclogging Irving Park and York roads in Bensenville, along with improvements for pedestrians. Bensonville $64 million 60105, 60106
Ogden Avenue flyover IDOT A new bridge over rail tracks on U.S. Highway 34 west of Illinois Highway 59 in Aurora that aims to avoid rail congestion as more trains run through the area. Aurora $27 million 60502, 60503, 60504, 60505, 60506, 60507, 60568, 60572, 60598
Ventra app Metra CTA, Metra and Pace will continue to roll out features including integrating fare payments across agencies. Plans include a trip-planning tool, ability to order and replace cards and use of smart phones instead of physical cards. Chicago Not available
111th St./Pullman station improvements Metra Cosmetic improvements — repairing of the wooden components and general painting — are planned to the 111th Street/Pullman Station on the Metra Electric Line. Pullman 150000 60628, 60643
Stewart Ridge station improvements Metra Repairs, including new deck boards, platform lighting and warming shelter replacement, and the rebuilding of the staircase, are planned on the Stewart Ridge Station on the Metra Electric Line, Blue Island branch. West Pullman Not available 60628, 60643
West Pullman station improvements Metra Repairs, including new deck boards, platform lighting, and the rebuilding of the staircase, are planned on the West Pullman Station on the Metra Electric Line, Blue Island branch. West Pullman Not available 60628, 60643
Calumet Metra station renovation Metra The Calumet Station on the Metra Electric Line will add a warming shelter, a new elevator and a newly renovated platform. The stairs at both ends of the station will be repaired as well. East Hazel Crest $5.5 million 60429
Riverside Station improvements Metra The historic clay tile roof on the depot at Riverside Station on the BSNF tracks will be rehabbed. Riverside 947000 60546
LaSalle St. Station improvements Metra The pavers and steel supports will be replaced at the LaSalle Street Station on the Rock Island District Line. Loop $2 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Ravinia Station improvements Metra Roof and painting work is planned at the Ravinia Station on the Union Pacific North Line. Highland Park, Glencoe part of a $500,000 project 60035, 60022
Metra station work Metra Accessibility improvements will be done at the West Chicago Station on Union Pacific West Line. West Chicago Not available 60185, 60186
Northbrook station renovations Metra Renovation work at the Northbrook Station on the Milwaukee District North Line includes new roof shingles, windows, doors and floors as well as concrete repairs. Northbrook 325000 60062, 60065
Mount Prospect station renovation Metra Roof repairs, window/doore replacements, painting, and handrail replacements are planned at the Mount Prospect Station on the Union Pacific Northwest Line. Mount Prospect 400000 60056
Metra station work Metra The platforms will be replaced at the Kedzie Station on the Union Pacific West Line. East Garfield Park Not available 60612, 60624
Villa Park station improvements Metra The platforms will be replaced at the Villa Park Station on the Union Pacific West Line. Villa Park Not available 60181
Winfield Station improvements Metra The platform will be replaced at the Winfield Station on the Union Pacific West Line. Winfield Not available 60190
Grayland station parking spaces Metra The platform will be replaced and 75 new parking spaces added at the Grayland Station on the Milwaukee District North Line. Old Irving Park $1.2 million 60618, 60630, 60641
Metra station work Metra Platform work will be finished at the Cumberland Station on the Union Pacific Northwest Line. Mount Prospect, Des Plaines Not available 60056
Metra station work Metra A new inbound shelter will be built at the Cary Station on the Union Pacific Northwest Line. Cary Not available 60013
123rd St. station work Metra Heated platforms will be tested at the 123rd Street Station on the Rock Island District Line. Blue Island 700000 60406
115th St./Kensington station improvements Metra Cosmetic improvements — repairing of the wooden components and general painting — are planned to the 115th Street/Kensington Station on the Metra Electric Line. Pullman Not available 60628, 60643
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Balmoral Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Foster Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Winnemac Avenue bridge. Ravenswood, Winnemac, Lincoln Square Part of $30 million project 60625, 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Lawrence Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Leland Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Wilson Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Sunnyside Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Montrose Avenue bridge. Ravenswood Part of $30 million project 60613, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Berteau Avenue bridge. Ravenswood, North Center Part of $30 million project 60613, 60618, 60640
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Irving Park Road bridge. North Center Part of $30 million project 60613, 60618
Metra bridge work Metra The next phase of Metra's Union Pacific North Line bridge work includes rebuilding the inbound tracks on the Grace Avenue bridge. North Center, Roscoe Village Part of $30 million project 60613, 60618
Metra station work Metra Work on the inbound half of the Ravenswood Station will take place. Ravenswood Not available 60613, 60640
Metra bridge work Metra The bridge at Morgan Street on the Rock Island District Line is slated to be replaced. Auburn Gresham, Washington Heights Not available 60620, 60628 and 60643
Metra bridge work Metra The bridge at 96th Street on the Rock Island District Line is slated to be replaced. Washington Heights $4 million 60620, 60628 and 60643
Metra bridge work Metra Embankment repairs at 51st Street on the Rock Island District line is slated to be done. Hyde Park Not available 60615, 60637
Metra bridge work Metra Embankment repairs at 57th Street on the Rock Island District line is slated to be done. Hyde Park Not available 60615, 60637
Metra bridge work Metra Bridge columns will be repaired at the 63rd Street bridge along the Metra Electric District Line. Hyde Park Not available 60615, 60637
Metra bridge work Metra Bridge columns will be repaired at the 64th Street bridge along the Metra Electric District Line. Hyde Park Not available 60615, 60637
Metra bridge work Metra Bridge columns will be repaired at the 67th Street bridge along the Metra Electric District Line. Greater Grand Crossing, South Shore Not available 60649, 60619, 60637
Metra bridge work Metra The bridge at 37th Street on the Rock Island District Line in Bronzeville will be raised and repaired. Bronzeville Not available 60653
Metra bridge work Metra The bridge at 39th Street on the Rock Island District Line in Bronzeville will be raised and repaired. Bronzeville Not available 60653
Metra road crossing work Metra The road crossing at Cedar Road in New Lenox along the Rock Island District Line will be replaced. New Lenox Not available 60451
Metra road crossing work Metra The road crossing at Vermont Street in Blue Island along the Rock Island District Line will be replaced. Blue Island Not available 60406
Metra road crossing work Metra The road crossing at 191st Street in Mokena on the Rock Island District Line will be replaced. Mokena Not available 60448
Metra road crossing work Metra The road crossing at Irving Park Road in Wood Dale on the Milwaukee District West Line will be replaced. Wood Dale Not available 60191, 60399
Metra road crossing work Metra The road crossing at Highland Avenue in Elgin along the Milwaukee District West Line will be replaced. Elgin Not available 60120, 60121, 60123, 60124
Metra road crossing work Metra The road crossing at York Road in Bensenville along the Milwaukee District West Line will be replaced. Bensenville Not available 60105, 60106
Metra road crossing work Metra The road crossing at Overlook Drive in Golf along the Milwaukee District North Line will be replaced. Niles, Glenview Not available 60714, 60025
Damen-Elston-Fullerton intersection CDOT The reconstruction of the six-way intersection at Damen, Elston and Fullerton avenues continues. This project realigns Elston and widens Damen and the sidewalk along Fullerton. All streets will be resurfaced. Wicker Park, Bucktown $17 million 60647, 60622, 60614
Belmont and Western CDOT The Western Avenue viaduct over Belmont Avenue will be replaced by a five-way intersection at Western, Belmont and Clybourn avenues. The project also includes repairs to the Western Avenue bridge over the North Branch of the Chicago River and improving lighting, traffic signals and sidewalks from north of Addison Street to south of Diversey Avenue. Roscoe Village, Avondale $25.6 million 60618
Riverwalk CDOT The final phase of the Riverwalk extends to Lake Street. The completed Riverwalk will reach 1.25 miles from Lake Shore Drive to Lake Street. Loop $103.7 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Pedestrian bridge CDOT A new S-shaped pedestrian and bike bridge over Lake Shore Drive will be built at 35th Street in Bronzeville. Bronzeville $18.3 million 60653
Pedestrian bridge CDOT A new pedestrian bridge will be built over Lake Shore Drive at 41st Street. Bronzeville Not available 60653
Pedestrian bridge CDOT A new pedestrian bridge will be built over Lake Shore Drive at 43rd Street. Bronzeville, Kenwood Not available 60653, 60615
Navy Pier flyover CDOT The flyover takes the lakefront path over Grand Avenue, Illinois Street and the Chicago River, where it had previously crossed at street level. Cost represents phase one price, of three-phase project. Navy Pier, Loop $23.8 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Adams Street bridge CDOT The bridge and viaduct over the Metra tracks at Union Station on Adams Street from Wacker Drive to Canal Street will be replaced. Access for pedestrians on Adams will be closed for two 30-day periods. Two lanes on Adams for cars will be closed for four months. Loop $25.6 million 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
U.S. Highway 45 work IDOT LaGrange Road will remain two lanes in both directions between 159th and 131st streets in Orland Park through fall as reconstruction and widening work are finished. Orland Park $95 million
Elgin intersection IDOT Construction to create a "single point" intersection at U.S. Highway 20 over McLean Boulevard in Elgin is complete with work continuing on McClean Boulevard. Elgin $44.4 million
Jane Byrne Interchange IDOT The new flyover from the inbound Dan Ryan Expressway to the outbound Eisenhower should be completed this year as part of the work on the former Circle Interchange. Also scheduled for 2016 are improvements to Taylor Street, Harrison Street and Halsted Street bridges. Night and weekend lane closures are expected. Chicago $475 million
Metra bridge work Metra The bridge at 18th Street on the Rock Island District Oine in the South Loop is slated to be replaced. Near South Side, South Loop, Lake Shore Drive Not available
Metra bridge work Metra The bridge at 55th Street on the Rock Island District Line in Hyde Park is slated to be replaced. Hyde Park Not available
27th St. Station improvements Metra The 27th St. Station on the Metra Electric Line will get new deckboards on the platform. Douglas Not available 60616
59th St. Station improvements Metra New deck boards on the platform of the 59th Street Station on the Metra Electric Line will be installed. Hyde Park Not available 60615, 60637
Lemont Station improvements Metra Platforms will be replaced at this station on the Heritage Corner. Lemont $1.4 million 60439
Glenview Station improvements Metra The Glenview Station on the Milwaukee District North line will have its doors and air conditioning unit replaced. Glenview Not available 60025, 60026
North Glenview Station improvements Metra Doors will be replaced at the North Glenview Station on the Milwaukee District North line. North Glenview Not available 60025, 60026
Mayfair Station improvements Metra At the Mayfair Station on the Milwaukee District North line, lighting will be replaced and two new shelters will be built. Mayfair Not available 60630
Big Timber Station improvements Metra On the Milwaukee West line, the Big Timber Station will have its platforms replaced. Elgin Not available 60121, 60120, 60123, 60124
Buffalo Grove Station improvements Metra Platform surfaces will be replaced at the Buffalo Grove Station on the North Central line. Buffalo Grove $5-600,000 60089
103rd St./Washington Heights Station improvements Metra Platforms will be replaced at this station on the Rock Island line. Washington Heights $1 million 60620, 60628, 60643
Prairie St. Station improvements Metra Platforms will be replaced at this station on the Rock Island line. Blue Island Not available 60406
Waukegan Station improvements Metra The Waukegan Station on the Union Pacific North line will have its bathrooms renovated and concrete replaced. Waukegan part of a $530,000 project 60085, 60087
Chicago Union Station improvements Metra The Madison St. entrance is being renovated at Union Station, and stairs and ceilings are being repaired. Loop 826000 60601, 60602, 60603, 60604, 60605, 60606, 60607, 60616
Metra bridge work Metra The rail fastening will be replaced on the steel deck bridge on Keeler and 24th. Cicero Not available 60804
Metra bridge work Metra The rail fastening will be replaced on the steel deck bridge on California and 18th. North Lawndale Not available 60608, 60623, 60624
Metra road crossing work Metra The road crossing at Stony Island Ave. and 70th St. in Chicago along the Metra Electric will be replaced. South Shore Not available 60649
North Ave. pedestrian bridge CDOT Renovation work on the North Ave. pedestrian bridge over N. Lake Shore Drive, including replacing the bridge deck and girders, will take place this spring. Lincoln Park $1 million 60614, 60610, 60611, 60642, 60654
Farnsworth Ave. Interchange Illinois Tollway The Farnsworth Avenue Bridge will be reconstructed over the Reagan Memorial Tollway (I-88) in Aurora with the goal of improving traffic flow. Aurora $19 million 60502, 60503, 60504, 60505, 60506, 60507, 60568, 60572, 60598
Veterans Memorial Tollway Illinois Tollway Construction to widen southbound I-355 between 71st and 75th Street will be completed by the end of 2016. Woodridge, Darien $8.4 million 60517, 60561
Your New Blue station work CTA Addison, Irving Park, Montrose, Harlem and Cumberland Blue Line stations to improve safety, security and comfort for customers. Improvements also include a new elevator at Addison. Irving Park $43 million 60641

Sources: IDOT, Illinois Tollway, CDOT, CTA, Metra, Pace

//apps.chicagotribune.com/chicago_construction_projects/js/vendor.min.js
(function(document) {
var CSS = [
“//apps.chicagotribune.com/chicago_construction_projects/css/styles.css”,
“//apps.chicagotribune.com/chicago_construction_projects/css/vendor.min.css”
];
CSS.forEach(function(url) {
var link = document.createElement(‘link’);
link.setAttribute(‘rel’, ‘stylesheet’);
link.setAttribute(‘href’, url);
document.head.appendChild(link);
});
})(document);
//apps.chicagotribune.com/chicago_construction_projects/js/app.min.js
(function(window, document, ConstructionProjectApp){
var MAP_CENTER = [41.8369, -87.6847];
var MAP_ZOOM = 10;
var MAP_TILE_URL_TEMPLATE = ‘http://{s}.tribapps.com/chicago-print/{z}/{x}/{y}.png’;
var MAP_TILE_SUBDOMAINS = [“maps1”];
var PROJECTS_JSON_URL = ‘//apps.chicagotribune.com/chicago_construction_projects/locations.json’;
var GEOCODER_URL = ‘https://qyf1ag22mj.execute-api.us-east-1.amazonaws.com/production/locations’;
var app = new ConstructionProjectApp({
container: document.getElementById(‘app-container’),
center: MAP_CENTER,
zoom: MAP_ZOOM,
tileURLTemplate: MAP_TILE_URL_TEMPLATE,
tileSubdomains: MAP_TILE_SUBDOMAINS,
projectsJsonUrl: PROJECTS_JSON_URL,
geocoderUrl: GEOCODER_URL
});
})(window, document, ConstructionProjectApp);